Source of NIT : Corporate Materials (EOC, Scope, PMI, NETRA)
State : Uttar Pradesh
Region : Corporate Center
NIT No. : CS-4140-155-2(R)
Brief NIT Description : Supply and Installation of Coal Handling Plant Package for Farakka Super Thermal Power Project , Stage-III (1x 500MW) at Nabarun, Dist- Murshidabad, State of West Bengal.
Contracts Classification : Equipment Supply & Erection
EMD Cost :
  0.00
  0.00
Tender Cost :
  6750.00
  150.00
Estimated Fee :
  0.00
  0.00
Date Of Issue of NIT : 19/11/2007
NIT Link: Click here to go to E-tender site E-Tender   
Document Sale Start Date : 19/11/2007 :00:00
Closing Date : 28/12/2007 :00:00
Bid Submission End Date : 16/01/2008 :00:00
Bid Opening Date : 16/01/2008 :11:00
Contact Person :
Contact Information : Designation: DGM (CS- Thermal-I)/ Manager (CS-Thermal-I)
NTPC LIMITED, 6th Floor, Engineering Office Complex,
A-8A, Sector-24, NOIDA - 201301, Distt. Gautam Budh Nagar (U.P.)
Phone:  0120-2596620,2410522
Fax:  0120-2410359,2410284,2410011
E-mail:  guptark@ntpceoc.co.in