COMBUSTION MODIFICATION PACKAGE
CM Barauni Stg-II, U# 8,9(2x250 MW) Package
Brief Scope of Work
The scope of the proposal for Engineering, Manufacture, Supply, Dismantling, Erection, Testing,
Commissioning works of Combustion Modification in Barauni Stg-II, U# 8,9(2x250 MW) Project
shall be on the basis of a single point responsibility, completely covering the following activities
and services in respect of all the equipment specified and covered under the specifications and
read in conjunction with “Scope of Supply & Services”, Part-A, Section – VI of Technical
Specification.
a) Detailed design of all the equipment and systems.
b) Providing engineering drawings, data, operation and maintenance Manuals, etc. for the
Employer’s approval.
c) Compliance with statutory requirements and obtaining clearances from statutory authorities,
wherever required.
d) Complete manufacturing including shop testing/type testing.
e) Packing and transportation from the manufacturer’s works to the site including customs
clearance/port clearance, port charges, if any.
f) Receipt, storage, preservation, handling and conservation of the equipment at the site.
g) Dismantling / removal/ modification of existing equipments like windbox, burner, damper,
piping, duct, structure etc as required and Supply & Erection of redesigned windbox, installation
of Separate over fire air panel(SOFA), SOFA duct along with related C&I equipment.
h) Fabrication, Pre-assembly (if any), erection, commissioning
&
completionof
combustionmodification including putting the unit under satisfactoryoperation of combustion
modification equipment.
i) Reliability tests and guarantee tests after successful completion ofcombustion modification
equipment.
j) Furnishing of spares on FOR site basis.