DARLIPALLI STPP- Stage-I (2x800MW) ADDITIONAL TOWNSHIP
PACKAGE
1. SALIENT TECHNICAL FEATURES
“Salient Technical Features of the equipment / systems / services covered in NIT
No.40087579 dated 10/07/2018, Bidding Document No. CS- 9549-364B-9 are
mentioned below. These Salient Technical features are mentioned only to facilitate the
prospective bidders to prima-facie understand the requirements under the tender and
the bidder shall not in any way limit or alter the scope of work and technical
features/specification of equipment/system/services covered in the Bidding Documents.
Detailed provisions in regard of scope of work and technical features/specification of
equipment/systems /services, contained in the Bidding Documents shall be final and
binding”.
LOCATION & APPROACH
NTPC Limited intends to develop Permanent Township for Darlipalli Super Thermal
Power Project Stage-I (2x800MW) at Darlipalli. The project is located in Sundargad
district. Nearby airport of Ranchi, Raipur & Bhubnaeshwar is at a distance of 220, 300 &
330 km respectively.
BRIEF SCOPE OF WORK OF TOWNSHIP PACKAGE
The brief scope of work under this package shall include the following facilities
(Residential & Non-Residential buildings, All works including Civil, Electrification, lifts,
piping, fire fighting etc.).
Sl.No. Description
No.of
Blocks/Details
1
B-Type (Stilt +7) 112 DUs
2
2
D-Type 48DUs
6
3
HOP Residence / GM’s Residence
4
4
Training Centre
1
5
Training Hostel
1
6
Hospital
1
7
Bal Bhawan Ladies Club & Nursery School
1
8
Higher Secondary School
1
9
Guest House Expansion
1
10
Shopping Centre
1
11
Union & Association Office
1
12
Community Centre
1
13
Executive Club
1
14
Swimming Pool
1
15
Stadium
1
16
Auditorium
1
17
Electrification Works
18
Fire Fighting System
19
HVAC / AC Works
20
Elevators
The facilities indicated above are indicative and may be changed during construction.
Page 2 of 6
2. TIME PERIOD FOR THE CONTRACT
Time Period for the Contract shall be 24 Months as per Work Schedule. Copy of Work
Schedule is enclosed at Annexure-A.
3. COMPENSATION FOR DELAY CLAUSE
(LD PARAMETERS)
S.No.
Period from
the date of
Letter of Award
Value of works
( as Cumulative %
of total value of
work ) to be
completed during
the period
Description of works in
progress / to
be completed during the period
1
Upto end of 6th
month from the
date of LOA
15%
- Complete mobilization at site
- Foundations & Stilt of B type
Completed.
- Foundations & I
st
Floor Slab of 2
blocks of D Type completed.
- Foundations of Hospital; School;
Guest House Ext.; Trainee Centre;
Trainee Hostel; Shopping Centre &
Auditorium Completed.
- Works in progress for all Residential
& Non-Residential buildings, Services
etc.
2
Upto end of 15th
month from the
date of LOA
65%
- Completion of
1. D Type 4 blocks
2. HOP Bunglow 1no.
3. HOD Bunglow 1no.
Works in progress
- Finishing works & Building Services
of all Residential & balance Non-
Residential buildings are in progress.
3
Upto end of 22th
month from the
date of LOA
95%
- Completion of
1. B Type.- 2 blocks
3. D Type – 6 blocks
4. HOP Bunglow.
5. HOD Bunglow-3 nos.
6. Trainee hostel
7. Hospital
8. Bal Bhawan
9. School
10. Shopping Centre
11. Guest House Ext.
12. Swimming Pool
13. Auditorium
Building finishes, Services &
Horticulture in progress.
4
Upto end of 24
th
month from the
date of LOA
100%
- Completion of all works
Page 3 of 6
4. CONTRACT PRICE ADJUSTMENT
FOR SCHEDULE- I: CIVIL WORKS
Fixed component 0.20
Labour component 0.15
Material component 0.35
Steel component 0.15
Cement component 0.10
Diesel component 0.05
FOR SCHEDULE- II: INTERNAL ELECTRIFICATION WORKS;
III: FIRE FIGHTING SYSTEM;
IV: AC WORKS &
V: ELEVATORS
Fixed component 0.30
Labour component 0.20
Material component 0.45
Diesel component 0.05
5. CONSTRUCTION WATER AND CONSTRUCTION POWER & STAFF/LABOUR
COLONY
1.0 The contractor shall arrange for construction water from underground/local
sources. All borings, pipe lines, pumps, water tankers, underground storage tank,
overground storage tank, etc, whatsoever required for taking the water from the
underground source to the site of work shall be provided / erected / constructed /
maintained by the contractor at his own cost.
2.0 The Contractor shall not be entitled to any compensation on account of the
expenditure incurred in arranging the construction water.
3.0 Contractor shall make the arrangement for construction power on his own cost.
However, NTPC may provide the Construction power as per the site availability,
but the Contractor is not entitled for any compensation on account of the quality
& availability of power from NTPC.
4.0 The contractor shall make his own arrangement for construction/ rented
premises for labour / staff colony.
Page 4 of 6
LIST OF SUGGESTED PLANT, EQUIPMENT AND MACHINERY
REQUIRED TO BE DEPLOYED BY CONTRACTOR AT SITE
---------------------------------------------------------------------------------------------------------------------
-----
S.No. Description Nos.
---------------------------------------------------------------------------------------------------------------------
-----
1. Mobile Crane - 20 MT / 8 MT As required
2. Trailers - 10 to 15 MT capacity 02
3. Diesel Power generator 125KVA capacity 1
4. Diesel Power generator 40KVA capacity 2
5. Diesel Power generator 10KVA capacity 4
6. Welding generator / rectifiers - 400A to 600A As required
7. Gas Cutting torches (complete set) 10
8. Lab equipment As per Part-C
9. Batching plant - 30Cum/Hr. 2
10. Concrete mixers 10 / 7 Cum/Hr. capacity (Electrically operated)10
11. Concrete mixers 10 / 7 Cum/Hr. capacity (Diesel operated) 5
12. Transit mixer - minimum 5.0 Cum capacity. 08
13. Concrete pump - 25 Cum / Hr. 04
14. Excavator (Poclain and J.C.B.) As required
15. Vibrators - Needle type 40mm (Electrically operated) 45
16. Vibrators - Needle type 25mm (Electrically operated) 10
17. Vibrators - Needle type 40mm (Petrol operated) 10
18. Vibrators - Float (Diesel Operated) 2
19. De-watering pumps 5 H.P (Electrically operated) 3
20. De-watering pumps 10 H.P (Electrically operated) 2
21. Bull Dozer (Heavy Duty) As required
22. Dumpers As required
23. Trucks As required
24. Scaffolding units As required
25. Service compressor with hose (Electrically operated) 2
26. Service compressor with hose (Diesel operated) 2
27. Floor polishing machine 10
28. Builder's Hoist (for concrete and other building material) 12
Page 5 of 6
-------------------------------------------------------------------------------------------------------------------
-----
S.No. Description Nos.
---------------------------------------------------------------------------------------------------------------------
-----
29. Portable Marble / Tile cutting machine 10
30. Stone Cutting / Polishing Workshop fixed with heavy duty
machines 1 setup
31. Total workstation for surveying including digital theodolite
and digital level 02
32. Plywood Shuttering / steel plates shuttering Minimum 15000sqm
(to be augmented as per site requirement)
33. Hand roller 05
34. Sheep foot roller As required
35. Road roller 10T 2
36. Road Paver 1
37. Water tankers with tractors 4
38. Electrical power winches for varying capacities 3
39. Tower Crane 6
40. Any other major equipment proposed to be used for the satisfactory
completion of work
NOTES :
a) These requirements and capacity of the equipment are indicative
only and not exhaustive and deployment of the equipment,
machinery and labour shall be suitably augmented to achieve the
timely completion of the work as per the program and directions of
the engineer, without any additional cost to Owner.
b) Other materials like cables, sling, gloves goggles, safety belts,
safety helmets, heating oven, pre-heating / post weld heat
treatment arrangements, material for making platforms and
platform supports etc. shall be mobilised as per requirement.
c) Other equipment though required for the timely completion of the
job and but not listed above shall be deployed by the contractor,
as per the job requirements and as directed by the Engineer.
d) The contractor shall make suitable provisions for repairs and
maintenance of the equipment mobilised and always keep them in
good working condition, as the repair facilities for such equipment
are not available at the project site.
e) All concreting shall be carried out using centralised batching plant,
transit mixers, concrete pumps. However individual mixers for
Page 6 of 6
localised concreting can be done for PCC work and small qty. of
RCC work after the approval of Engineer-in-charge, if required.