AIR CONDITIONING SYSTEM PACKAGE FOR AUXILARY BUILDINGS
FOR
NABINAGAR SUPER THERMAL POWER PROJECT (3X660 MW)
BIDDING DOCUMENT NO. : CS-0370-147A(R)-2
Salient Technical Features of the Equipments/ Systems/ Services covered in NIT/IFB
No. 40082885 dated 01.11.2017 are mentioned below.
These Salient Technical Features are mentioned only to facilitate the prospective
Bidders to prima-facie understand the requirements under the tender and shall not in
any way limit or alter the Scope of Work and Technical Features/ Specification of
Equipments/ Systems/ Services covered in the Bidding Documents. Detailed
provisions in regard of Scope of Work and Technical Features/ Specification of
Equipments/ Systems/ Services, contained in the Bidding Document shall be final
and binding.
SALIENT TECHNICAL FEATURES
1.0
SCOPE OF WORK
The broad scope of work includes design, engineering, manufacture, testing at works,
delivery and storage at site, erection, testing and commissioning of following:
a) All air-conditioning equipments for office areas in service building, administrative
building, auditorium building, canteen building and other PLC/Microprocessor/ controller
integrated GIU based control room.
2.0
BRIEF DESCRIPTION OF AIR-CONDITIONING SYSTEM
It is proposed to provide Screw chilling machines to meet the air conditioning requirement
of all the air conditioned areas of Service building and Administrative building. Further, air-
conditioning requirement of Auditorium and canteen would be met with air-cooled
condensing machines. Other DCS/PLC based control rooms of auxiliary buildings would
be air-conditioned using split (non-Ductable) air conditioners. Dining hall in Administrative
building would be air-conditioned using Cassette (non-Ductable) air conditioners. Details of
major areas to be air conditioned and the equipments proposed to be provided are
elaborated in the following para.
2.1
A/C Plant for Service building.
2.1.1
The A/C system would comprise of:
(i) 2 x 165 TR capacity screw compression type chilling machine.
(ii) Two (02) Nos. of primary chilled water pumps.
(iii) Two (02) Nos. of variable frequency driven (VFD) Secondary chilled water pumps
(iv) Two (02) Nos. of condenser water pumps.
Page 2 of 2
(v) Two (02) Nos. of variable frequency driven (VFD) cooling towers.
(vi) Nine (9) nos. of variable frequency driven (VFD) air handling units (AHUs)
(vii) Interconnecting piping, duct work, insulation, cabling, PLC/Microprocessor based
control panel, instrumentation, etc.
2.2
A/C Plant for Administrative building.
2.2.1
The A/C system would comprise of:
(i) 2 x 165 TR capacity screw compression type chilling machine.
(ii) Two (02) Nos. of primary chilled water pumps.
(iii) Two (02) Nos. of variable frequency driven (VFD) Secondary chilled water pumps
(iv) Two (02) Nos. of condenser water pumps.
(v) Two (02) Nos. of variable frequency driven (VFD) cooling towers.
(vi) Ten (10) nos. of variable frequency driven (VFD) air handling units (AHUs)
(vii) Interconnecting piping, duct work, insulation, cabling, PLC/Microprocessor based
control panel, instrumentation, etc.
2.3
AC Plant for Auditorium.
2.3.1
The AC system would comprise of
(i) 2 x 30 TR capacity air cooled type condensing machine.
(ii) Two (02) Nos. of variable frequency driven (VFD) air handling units (AHUs)
(iii)Interconnecting piping, duct work, insulation, cabling, PLC/Microprocessor/GIU based
control panel, instrumentation, etc.
2.4
AC Plant for Canteen.
2.4.1
The AC system would comprise of
(i) 2 x 30 TR capacity air cooled type condensing machine.
(ii) Two (02) Nos. of variable frequency driven (VFD) air handling units (AHUs)
(iii)Interconnecting piping, duct work, insulation, cabling, PLC/Microprocessor/GIU based
control panel, instrumentation, etc.
2.5
Non-Ductable Split Air-Conditioners.
2.5.1
AC plant control room in Administrative building, Service building, Auditorium
building, Canteen building.
(i) 8 x 3 TR Non Ductable (Split).
2.5.2
Dining hall in Administrative building.
(i) 2 x 4 TR Non - Ductable Cassette.