Salient Features

NTPC LIMITED

PROJECT

Corporate Centre, EOC

PACKAGE NAME

CONSULTANCY PACKAGE FOR REVIEW OF TECHNICAL SPECIFICATIONS

“Salient Features of the services covered in IFB CS-0011-703-9 dated 18/08/2016 e tender no: 40061687 are mentioned below. These Salient Features are mentioned only to facilitate the prospective bidders to prima-facie understand the requirements under the tender and shall not in any way limit or alter the scope of work and features / ToR / requirement of systems / services covered in the Bidding Documents. Detailed provisions in regard of scope of work and features / ToR / requirement of systems / services, contained in the Bidding Documents shall be final and binding.”

Brief Scope of Service

a) Audit of present Engineering systems, IT infrastructure and availability of Engineering software, computational tools and suggest up gradation required in line with international best practices.

b) Review & audit of presently followed design concepts, design criteria, provision of redundancies, design margins and benchmarking NTPC practices with best practices, including but not limited to following:

i) Cycle component optimization, optimization of steam parameters, condenser vacuum, waste heat utilization and unit size optimization.

ii) Review of performance guarantees and bid evaluation parameters for various power plant equipment/ system.

iii) Review of NTPC technical specifications of complete Super Critical Power Project having unit size of 660 MW/ 800 MW for following packaging concept:

- EPC Mode

- Island package Mode (TG, SG and BOP island)

- Package Mode (Typically 30 Packages)

NTPC shall provide one set each of typical specifications in above packaging mode to carry out above consultancy assignment.

iv) Recommendations on specific requirements to be built up in technical specifications to take care of changes brought out in recent CERC tariff order of 2014-19 and requirements of Indian Electricity Grid Code.

v) Recommendations on specific requirements to be incorporated in technical specifications to take care of recent revised environment norms dated 07-12-2015 with specific reference to NOx & SOx.

c) Study & review of process & system of cost estimation of various mechanical, electrical, C&I and civil packages associated with typical 660 MW/ 800 MW super critical thermal power project.

d) Typical organogram of Engineering set up at Corporate / Regional level for handling @ 5000MW/Year of capacity addition and the cost of manpower required to be invested by the company.