“Salient Technical Features of the equipment/systems/services covered in NIT No. CS-5505-908(R2)-2 dated 06.05.2015 are mentioned below. These Salient Technical Features are mentioned only to facilitate the prospective bidders to prima-facie understand the requirements under the tender and shall not in any way limit or alter the scope of work and technical features/specification of equipment/ systems/ services covered in the Bidding Documents. Detailed provisions in regard of scope of work and technical features/ specification of equipment/ systems/ services, contained in the Bidding Documents shall be final and binding.”
LOCATION |
|||
a) |
State |
- |
Uttarakhand |
b) |
District |
- |
Chamoli |
c) |
Tehsil |
Joshimath |
|
d) |
Latitude & Longitude at barrage |
- |
Latitude : N 30° 29˘ 30˛ Longitude : E 79° 37˘ 30˛ |
e) |
River |
- |
Dhauliganga (Tributary of Alaknanda) |
HEAD RACE TUNNEL |
|||
a) |
Length and shape |
- |
12.087 km, Horse shoe/ Circular |
b) |
Diameter |
- |
5.64 m |
c) |
Design discharge |
- |
122.18 cumecs |
d) |
Velocity |
- |
4.96 m/sec |
e) |
Number of intermediate adits |
- |
3 |
PRESENT STATUS OF HEAD RACE TUNNEL PACKAGE WORKS
Sl. No. |
Description of work |
Present Status |
1 |
Excavation of Intake adit |
Completed |
2 |
Excavation of TBM Entry Adit |
Completed |
3 |
Excavation of Branch Adit |
Completed |
4 |
Excavation of TBM Exit Adit (Charmi adit) |
193m left |
5 |
Excavation of HRT by Drill and Blast Method |
· HRT excavation from RD 14.5m to 1911.5m has been carried out from intake adit. · HRT excavation from RD 2798m to 2939m has been carried out from Branch Adit · HRT Excavation from RD 11914m to RD 12087 has been carried out from surge shaft adit. |
6 |
Tunnel Concrete lining works in Drill and Blast Portion of HRT |
· Overt lining works carried out from RD 23m to RD 207m and RD 218m to 230m in HRT U/s of Intake adit. · About 72m overt lining has been carried out from surge shaft end |
7 |
Excavation of HRT by TBM |
Excavation of HRT by TBM has been carried out from RD 11914m to RD 6482m (5432m), Precast lining has also been erected in this reach. |
8 |
Present status of TBM |
Presently TBM is standing in an area having multiple weak zones. A top heading has been created above TBM from 9 O’clock to 3 O’clock. |