Bid Invitation No. 40032052
Vehicle Parking Shed near
1.0The owner desires to Vehicle Parking Shed near
2.0This technical specification covers civil and structural works. The works shall have to be carried out both below and above ground level. The works shall be carried out within the Plant boundaries unless otherwise specified. Broad scope of work is specified herein in subsequent clauses.
3.0The bidder is expected to get all doubts clarified in respect of interpretation of any portion of these documents before tendering, in writing with the Owner.
4.0SCOPE OF WORK
The works to be performed under this specification includes construction, providing all labour, materials, consumables, construction equipment, temporary works, temporary storage sheds, temporary site offices, construction plants, fuel supply, tools and plant, scaffolding, supplies, transportation, all incidental items not shown or specified but reasonably implied or as necessary for successful completion of the works including contractor’s supervision and in strict accordance with the drawings and specifications including revisions and amendments there to, as may be required during the execution of Vehicle Parking Shed near
5.0All the materials required for the completion of work stated or sufficiently implied in the BOQ shall be provided by the Bidder. The scope shall also include setting up by the Bidder a complete testing laboratory in the field to carry out all relevant tests required for the execution of the project. Alternatively, the successful bidder can also engage existing Engineering college or identified labs for the purpose of carrying out test specified or identified in the Field Quality Plan.
6.0The work shall be carried out in accordance with tender drawings, technical specifications, schedule of items, other tender documents, and directions of the
7.0Item / items of work though specified in the schedule of item but for which detailed specifications are not given in the technical specifications, shall be performed as per CPWD or State PWD Specifications and best available industry practices.
8.0Layout and levels of all structures shall be made by the Bidder at his own cost from general grid of the plot and nearest GIS bench mark or other acceptable bench mark of government's department or as per directions of the Engineer. The bidder shall give all help in providing all instruments, materials and personnel to the engineer for checking the layout and correctness of layout & levels. No extra payment shall be paid to the bidder in what so ever manner on this account. The Bidder shall be solely responsible for the correctness of the layout and levels.