|
NTPC LIMITED |
PROJECT |
: BARETHI STPP (4x660 MW) |
PACKAGE NAME |
: MAIN PLANT TURNKEY PACKAGE |
“Salient Technical Features of the equipment/systems/services covered in IFB No. 40031210 dated 31.12.2014, Bidding Document No.
ABRIEF SCOPE OF WORK
The Brief scope of work for the subject Main Plant Turnkey Package for Barethi STPP,
Design, Engineering, Manufacture, Supply, Construction, Erection, Testing & Commissioning works for the Main Plant Turnkey Package for Barethi Super Thermal Power Project,
a)Basic Engineering of the plant;
b)Detailed design of all the equipment and equipment system(s) including civil, structure steel & Architectural works included in bidder's scope.
c)Providing engineering drawings, equipment sizing & performance data, instruction manuals, as built drawings and other information;
d)Compliance with statutory requirements and obtaining clearances from statutory authorities, wherever required;
e)Complete manufacturing including shop testing/type testing;
f)The Civil, structural and architectural works including topographical survey, Complete site levelling, construction water for plant area, water supply and sanitation, infrastructure works including major roads, drains as envisaged in tender GLP, Effluent &sewage treatment facility for plant, main plant area structures and foundations including turbine building, bunker building, boiler structure, ESP structure, service building, compressor house, coal conveying facilities, Ash handling plant, chimney, pipe/cable galleries and pipe/cable trenches, duct banks, pedestals, other buildings and structures, transformer yard structures, switchyard structures, fuel oil handling system and fire protection system (Partly) structures and foundations, bridges and culverts for crossing of roads / Rail Tracks inside plant area, landscaping and other miscellaneous buildings and structures.
g)Packing and transportation from the manufacturer’s works to the site including logistic studies, insurance, customs clearance & port clearance, port charges, if any.
Page 1 of 8
h)Receipt, storage, preservation, handling and conservation of equipment at the site;
i)Fabrication,
j)Performance and guarantee tests after successful completion of initial operation;
k)Supply of spares on FOR site basis;
l)Reconciliation with Customs Authorities, in case of foreign Bidders;
m)Satisfactory conclusion of the Contract;
n)Insurance and other requirements
Detailed scope of work has been specified in the bidding documents.
B SALIENT TECHNICAL FEATURES
1.00.00Steam Generator
1.01.00Type
The Steam Generator shall be of single pass (Tower type) or two pass type using either spiral wall (inclined) or vertical plain / rifled type water wall tubing.
1.02.00Other Features of Steam Generator Design
The Steam Generator shall be direct pulverized coal fired, top supported, single reheat, radiant, dry bottom, with balance draft furnace and shall be suitable for outdoor installation. The evaporator of Steam Generator shall be suitable for variable pressure operation from subcritical to supercritical pressure range.
1.03.00Rating of Steam Generator(s)
Steam Generator shall be designed to cater to duty requirements at Boiler Maximum Continuous Rating (BMCR) specified below:
Capacity |
of Steam |
Steam Flow |
Temp. |
|
|
|
Pressure |
|
|
||||
Generator and Rated |
(T/Hr) |
|
(Deg C) |
|
|
|
Kg/cm2(a) |
|
|||||
Steam parameters: |
|
|
|
|
|
|
|
|
|
|
|
||
i) |
At |
102% of |
the |
To |
achieve |
turbine |
To achieve turbine |
||||||
outlet |
|
|
turbine |
VWO |
throttle |
main |
steam |
throttle |
|
steam |
|||
|
|
|
steamflow |
|
temperature |
|
as |
pressure |
|
as |
|||
|
|
|
requirement. |
indicated |
in |
clause |
indicated in clause |
||||||
|
|
|
|
|
3.02.00. |
The |
steam |
3.02.00. the steam |
|||||
|
|
|
|
|
temperature |
|
at |
pressure |
|
at |
|||
|
|
|
|
|
Superheater |
|
outlet |
superheater |
outlet |
||||
|
|
|
|
|
shall |
be |
atleast |
3°C |
shall |
be |
atleast 9 |
||
|
|
|
|
|
higher than the |
rated |
kg/Cm2 |
|
higher |
||||
|
|
|
|
|
main |
|
|
steam |
than |
the |
rated |
||
|
|
|
|
|
temperature |
at |
HP |
main |
|
|
steam |
||
|
|
|
|
|
turbine inlet. |
|
|
pressure |
at HP |
||||
|
|
|
|
|
|
|
|
|
|
turbine inlet |
|
Page 2 of 8
ii) At |
- |
To achieve reheat steam |
|||||
|
|
temperature |
at |
Turbine |
|
||
|
|
Inlet |
as indicated |
in |
|
||
|
|
clause |
3.02.00 |
of |
this |
|
|
|
|
|
|||||
|
|
temperature |
at |
reheater |
|
||
|
|
outlet shall be atleast 3oC |
|
||||
|
|
higher |
than |
the rated |
|
||
|
|
reheat |
|
|
steam |
|
|
|
|
temperature at IP turbine |
|
||||
|
|
inlet. |
|
|
|
|
|
iii) Feed Water Temp. |
|
To be optimized by the |
|
||||
at Economizer Inlet |
|
bidder |
but |
not |
less |
|
|
|
|
than 285oC |
|
|
|
|
1.04.00Limiting Parameters for Steam Generator Design
The Steam Generator design shall comply with the following limiting parameters with ‘design coal’ firing, under stipulated ambient air condition i.e. 27 degree Celsius temperature and 60 % relative humidity:
|
|
Flue gas temperature at |
125oC (minimum) |
|||||
|
|
(Corrected) at 105% TMCR & 100 % TMCR load |
||||||
1.05.00 |
Operating Requirements |
|
|
|||||
|
|
|
|
|
|
|
||
|
1. |
|
Minimum |
load |
without oil |
40% BMCR |
||
|
|
|
support for flame stabilization |
|
|
|||
|
2. |
|
Operation without HP heaters in |
Steam generator shall also be designed for |
||||
|
|
|
service |
|
|
|
continuous operation with HP heaters out of |
|
|
|
|
|
|
|
|
operation. The steam generator heat output |
|
|
|
|
|
|
|
|
under HP heaters out condition shall be at least |
|
|
|
|
|
|
|
|
100% BMCR heat output with HP heater in |
|
|
|
|
|
|
|
|
service. |
|
|
3. |
|
Steam generator control range |
The automatic control range of Steam |
||||
|
|
|
|
|
|
|
Generator shall be from 50% TMCR to 100% |
|
|
|
|
|
|
|
|
BMCR. Under the above control range, the |
|
|
|
|
|
|
|
|
steam temperatures at SH & RH outlets shall |
|
|
|
|
|
|
|
|
be maintained at their rated values. |
|
|
4. |
|
Mode |
of |
Steam |
Generator |
The Steam Generators shall be designed for |
|
|
|
|
Operation |
|
|
variable pressure operation. Thermal design of |
||
|
|
|
|
|
|
|
Steam Generator and the selection of materials |
|
|
|
|
|
|
|
|
shall be suitable for variable pressure |
|
|
|
|
|
|
|
|
operational modes. |
|
|
5 |
|
Rate of loading / unloading |
|
|
|||
|
|
|
a) |
Step load change |
Minimum + 10% per minute |
|||
|
|
|
b) |
Ramp Rate |
|
(i) Minimum + 3% per minute (30% to 50% |
||
|
|
|
|
|
|
|
|
load) |
|
|
|
|
|
|
|
(ii) |
Minimum + 5% per minute (50% to 100% |
|
|
|
|
|
|
|
|
load) |
Page 3 of 8
1.06.00Coal data/Fuel Oil System
The primary fuel for the main steam generator shall be coal. Heavy Fuel Oil (HFO) shall be used for
2.00.00 Electrostatic Precipitator (ESP)
2.01.00 System Description:
The Electrostatic Precipitators shall be of outdoor type and installed on the cold end side of regenerative air preheaters. The flue gas shall be drawn from air preheater outlets of the balanced draft, pulverized coal fired Steam Generator and guided through adequately sized duct work into the specified number of independent gas streams of each ESP. Similarly, the flue gas after the Electrostatic Precipitators shall be led to the suction of the induced draft fans.
2.02.00Service Conditions
The Steam Generators are designed to burn pulverised coal. HFO shall be used during startup and at low loads for warm up and flame stablisation of Steam Generator. Further, Light Diesel Oil (LDO) shall be used to facilitate black start of units when no auxiliary steam is available from external source.The ESP shall be designed to remove fly ash particles (to meet the stipulated ESP emission levels) from the flue gas generated in the Steam Generator with pulverized coal firing.
3.00.00 Steam Turbine
3.01.00Type
The steam turbine shall be tandem compound, single reheat, regenerative, condensing,
3.02.00Rating
The steam turbine generator unit shall conform to the following design and duty conditions:
1. |
Output under |
economic |
maximum |
: |
660 MW |
|
continuous rating |
(EMCR) |
(guaranteed |
|
|
|
output load) at generator terminals |
|
|
||
2. |
Turbine throttle steam pressure |
: |
247 to 270 Kg/cm2 (abs) |
||
|
|
|
|
|
(Bidder to optimize) |
3. |
Turbine throttle main steam temp. |
: |
565 to 600 oC |
||
|
|
|
|
|
(Bidder to optimize) |
4. |
Reheat steam temp. at turbine inlet |
: |
593 to 600oC |
||
|
|
|
|
|
(Bidder to optimize) |
Page 4 of 8
5. |
Condenser pressure |
: |
77 mm Hg (abs) |
6. |
Turbine speed |
: |
3000 rpm |
7. |
Frequency variation range around rated |
: |
+ 3% to - 5% (47.5 Hz to 51.5 |
|
frequency of 50 Hz |
|
Hz) |
3.03.00 Other Features
Turbine shall be capable of operating continuously with valves wide open (V.W.O.) to swallow at least 105% of EMCR steam flow to the turbine at rated main steam and reheat steam parameters and also the corresponding output shall not be less than 105% of rated load with 3% make up and 77 mm Hg (abs) condenser pressure.
The steam turbine shall have minimum seven uncontrolled extractions for regenerative feed heating based on optimised cycle and shall be suitable for satisfactory operation under tropical conditions.
4.00.00 Generator
4.01.00Type
Three phase, horizontal mounted, indoor installed,
4.02.00Rating
Generator and its excitation system shall have a capability at least matching the declared maximum continuous rated output of the associated steam turbine (for the designed secondary cooling water temperature) at all power factors between 0.85 lagging and 0.95 leading with +3% to
4.03.00Also the generator and its excitation system shall be capable of continuous stable operation without any excessive temperature rise at the peak output of the associated steam turbine under VWO & HP heater out condition, etc. as available for the designed secondary cooling water temperature, at all power factors between 0.85 lagging and 0.95 leading with +3% to
4.04.00Rated Parameters
1. |
Power Factor |
- |
0.85 (lag) |
2. |
Terminal voltage |
- |
In the 18 to 27 kV range |
3. |
Frequency |
- |
50 Hz |
4. |
Speed |
- |
3000 rpm |
5. |
Short circuit ratio |
- |
Not less than 0.48 (without any |
|
|
|
tolerance) |
Page 5 of 8
5.00.00Ash Handling Plant
Ash handling system consists of the following sub systems:
a)Bottom Ash Handling System
i)Jet pump and Water Impounded Hopper System – An intermittent system consisting of water impounded hoppers, clinker grinders, jet pumps, etc.
OR
ii)Submerged Scrapper Conveyor and dry type hopper System – A continuous system consisting of dry type Bottom Ash hoppers, submerged scrapper conveyors, clinker grinders, bottom ash slurry trench, slurry transportation pumps, etc.
b)Dry Fly Ash Conveying system
Two alternatives for pneumatic conveying system are specified for conveying of fly ash in dry form from ESP hoppers upto buffer hoppers. i.e. vacuum conveying system or pressure conveying system
i)Vacuum Conveying System
It shall consist of liquid ring vacuum pumps, material handling valves, cast iron and MS pipes, instrument air compressors etc.
OR
ii)Pressure Conveying System
It shall consist of screw compressors, air lock/pump tanks, ash intake & discharge valves, CI, MS pipes, instrument air compressors etc.
c)Dry Fly Ash Transportation system
The dry fly ash from the buffer hoppers in each unit shall be transported to either silos for slurry disposal system or to storage silos. The user industries shall take the dry fly ash from storage silos either in closed tankers or in open tankers.
d)Ash Disposal System
i)Bottom ash, economizer ash and air preheater ash (if applicable) shall be disposed offfrom ash slurry sump to ash disposal area by bottom ash slurry disposal pumps.
ii) The fly ash and air preheater ash (if applicable) shall be disposed off by high concentration slurry disposal (HCSD) system. In high concentration slurry disposal (HCSD), fly ash shall be mixed with water in suitable proportions to form high concentration slurry. The slurry shall be pumped to the disposal area by means of positive displacement pumps.
6.00.00Coal conveying facilities, Fire detection & protection system, Compressed air system, A/C and ventilation system, Hydrogen generation system, Condensate Polishing system shall be as per the scope of technical specification.
Page 6 of 8
7.00.00Electrical Systems
The electrical items shall cover following:
Generator, Excitation System and its Auxiliary Systems
Motors, Electric Actuators
Generator Busducts, MV Busducts and Generator Circuit Breaker (if applicable).
Power Transformers, Auxiliary Oil Filled Transformers, Indoor Transformers
MV Switchgears, LV Switchgears and LV Busducts, Numerical Relay Networking, DC System, Battery and Battery Charger
HT Power Cables, LT Power and Control Cables, Cabling, Earthing and Lightning Protection, Lighting, DG Sets
765/132 KV AIS.
Control & Protection of EHV system and Generator Relay Panels, Substation Automation System (SAS) based on IEC 61850 protocols.
Construction Power facilities
Type Testing and Mandatory Spares as specified.
8.00.00 C & I Systems
The control system, called Distributed Digital Control Monitoring & Information system (DDCMIS) is envisaged to be procured under this package for control and operation of
Integral control & protection of boiler including Burner Management System and Boiler protection system.
The integral control & protection of Steam Turbine Generator including
Modulating controls of the Steam Generator (SG) {Combustion Control- Fuel Flow/Air Flow; Furnace Draft Control, FW flow control etc.}.
Modulating controls of Feedwater& Condensate Cycle {Hotwell level control, Deaerater Level control, Heater Level Control, etc.}.
Binary control of auxiliaries of Steam Generator (SG) {Forced draft (FD) fan, Induced Draft (ID) Fan, Primary Air (PA) Fan etc.}.
Binary control of auxiliaries of Turbine Generator (TG) {Boiler Feed Pump (BFP), Condensate Extraction Pump (CEP) etc.}.
Electrical Breaker including synchronization circuits.
Air Conditioning and Ventilation systems.
Ash Handling Plant.
Page 7 of 8
Human Machine Interface & Plant Information System (HMIPIS) is based on Large Video Screen (LVS) displays supported by TFT monitor based Operator Work Stations (OWS). These devices through customized
The sequence of events recording & alarm annunciation are also implemented as a part of DDCMIS system. A GPS based master and slave clock system is to be provided for uniform and synchronized timing signals throughout the entire station.
The power supply for the control system is based on 24V DC provided through microprocessor based modular charger system and for the peripherals and other subsystem through 230V Single Phase UPS.
Main Equipment related instruments like Flame Monitoring system, Coal Bunker Level measurement system, gravimetric feeder control system, Acoustic Pyrometer, Acoustic Steam Leak detection system, Furnace and Flame viewing system, Turbine stress control / evaluation system, Turbine supervisory and diagnostic system etc are also procured through this package.
Field instruments like pressure, DP, flow & level transmitter, analyzers along with their process connection & piping as well as measurement systems like vibration monitoring system etc are also procured through this package.
A
Apart from above, an
9.00.0Civil Works
The site for Plant and offsite areas comprises of layers of silty clay / clayey silt and sand/weathered rock layer at deeper depths. Open foundation and pile foundation are envisaged for major structures. The steel structures shall be
10.00.0SOLAR P.V Plants
Solar
Page 8 of 8