ANNEXURE-A
SALIENT TECHNICAL FEATURES
SUB: REVIVAL / RECOMMISSIONING OF AUTO COAL SAMPLER UNIT OF CHP ST-II
INTRODUCTION:
TALCHER SUPER THERMAL POWER STATION OR NTPC TALCHER KANIHA (TSTPP) IS LOCATED IN TALCHER SUBDIVISION OF ANGUL DISTRICT IN ODISHA STATE ON NH 202. THIS POWER PLANT IS COAL BASED POWER STATION. IT OPERATES 6 UNITS OF 500 MW TO A TOTAL CAPACITY PRODUCTION OF 3,000 MW. THE CORE ACTIVITY IS GENERATION OF ELECTRICITY.
NEAREST TOWN – TALCHER (26 KM)
NEAREST RAILWAY STATION – TALCHER (29 KM)
NEAREST AIRPORT – BHUBANESWAR (180 KM)
INSTALLED CAPACITY:
STAGE – I : 2 X 500 MW
STAGE – II : 4 X 500 MW
AREA OF WORK
REVIVAL / RECOMMISSIONING OF EXISTING COAL SAMPLING UNIT ST-II CHP
BRIEF SCOPE OF WORK:
THE JOB IS A TWO PART COMPRISING OF MATERIAL SUPPLY AND SERVICES WITH DEPUTATION OF SERVICE ENGINEER FOR SUPERVISION OF ERECTION AND COMMISSIONING ACTIVITIES (INCL MECHANICAL, ELECTRICAL AND C&I)