BALANCE WORKS OF
MAIN PLANT, CW AND OFFSITE CIVIL WORKS PACKAGE FOR BONGAIGAON THERMAL POWER PROJECT
Salient Technical features of the equipment/ systems/ services covered in the NIT No.
Salient Technical Features:
The work shall cover the following civil/ structural items:
1)Piling work (estimated quantity: 1,400 RM)
2)RCC/PCC work (estimated quantity: 140,075 Cu M)
3)Fabrication of steel structures at BgTPP site (estimate quantity: 7,200 MT)
4)Fabrication of steel structures at Guwahati fabrication yard (estimate quantity: 4,600 MT)
5)Transportation of fabricated steel structures / Cut pieces of structural steel from Guwahati fabrication yard to BgTPP site (estimate quantity: 13,000 MT)
6)Erection of steel structures (estimate quantity: 23,700 MT)