SALIENT TECHNICAL FEATURES OF HEAD RACE TUNNEL (BALANCE WORK) PACKAGE FOR TAPOVAN VISHNUGAD HYDRO ELECTRIC POWER PROJECT (4X130 MW)

“Salient Technical Features of the equipment/systems/services covered in NIT No. CS-5505-908(R1)-2 dated 15.05.2014 are mentioned below. These Salient Technical Features are mentioned only to facilitate the prospective bidders to prima-facie understand the requirements under the tender and shall not in any way limit or alter the scope of work and technical features/specification of equipment/ systems/ services covered in the Bidding Documents. Detailed provisions in regard of scope of work and technical features/ specification of equipment/ systems/ services, contained in the Bidding Documents shall be final and binding.”

SALIENT TECHNICAL FEATURES

LOCATION

 

a)

 

State

 

-

Uttarakhand

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

b)

 

District

 

-

Chamoli

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

c)

 

Tehsil

 

-

Joshimath

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

d)

 

Latitude & Longitude at barrage

-

Latitude : N 30 29 30

 

 

 

 

 

 

Longitude : E 79 37 30

 

e)

 

River

 

-

Dhauliganga (Tributary of Alaknanda)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

HEAD RACE TUNNEL

 

 

 

a)

 

Length and shape

-

12.087 km, Horse shoe/ Circular

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

b)

 

Diameter

 

-

5.64 m

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

c)

 

Design discharge

-

122.18 cumecs

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

d)

 

Velocity

 

-

4.96 m/sec

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

e)

 

Number of intermediate adits

-

3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

PRESENT STATUS OF HEAD RACE TUNNEL PACKAGE WORKS

 

 

 

 

 

 

 

 

Sl.

 

 

Description of work

 

Present Status

 

No.

 

 

 

 

 

 

 

 

1

 

 

Excavation of Intake adit

 

Completed

 

 

 

 

 

 

 

 

2

 

 

Excavation of TBM Entry Adit

 

Completed

 

 

 

 

 

 

3

Excavation of Branch Adit

 

Completed

 

 

 

 

 

4

Excavation of TBM Exit Adit (Charmi

193m left

 

 

 

 

 

adit)

 

 

 

Sl.

Description of work

 

Present Status

No.

 

 

 

 

5

Excavation of HRT by Drill and Blast

 

HRT excavation from RD 14.5m to

 

Method

 

1911.5m has been carried out from intake

 

 

 

adit.

 

 

 

HRT excavation from RD 2798m to

 

 

 

2939m has been carried out from Branch

 

 

 

Adit

 

 

HRT Excavation from RD 11914m to RD

 

 

 

12087 has been carried out from surge

 

 

 

shaft adit.

6

Tunnel Concrete lining works in Drill

Overt lining works carried out from RD

 

and Blast Portion of HRT

 

23m to RD 207m and RD 218m to 230m

 

 

 

in HRT U/s of Intake adit.

 

 

About 72m overt lining has been carried

 

 

 

out from surge shaft end.

7

Excavation of HRT by TBM

Excavation of HRT by TBM has been carried

 

 

out from RD 11914m to RD 6482m (5432m),

 

 

precast lining has also been erected in this

 

 

reach.

8

Present status of TBM

Presently TBM is standing in an area having

 

 

multiple weak zones. A top heading has been

 

 

created above TBM from 9 O’clock to 3

 

 

O’clock.