Enquiry No.: 201300050 Date: 05/01/2021
Sub: Procurement of Acid Resistant Brick Lining Material for DM Plant, CT Area
Corporate Identification Number: U40105DL2005 PTC138458
Registered Office : NTPC Bhawan, Core-7, SCOPE Complex 7, Institutional Area, Lodi Road, New Delhi 110003
Noida Office : The Landmark, Second Floor, Plot No. A35, Sector 2, Noida-201301 (U.P), Tel: 0120- 4148900, Fax: 0120-4148913
Mumbai Office : Samruddhi Venture Park, 5th Floor, MIDC, Marol, Andheri (E), Mumbai - 400093. Tel: 022- 28216613, Fax: 022-28269057
Project Site : PO RGPPL Anjanwel, Taluka Guhagar, Distt. Ratnagiri (Maharashtra) 415634, Tel: 02359- 241073, Fax: 02359- 241118
D. Technical Specifications
E. Special Terms & Conditions
F. Instructions to Bidders (ITB)
G. Forms and Annexures
5.2 The Bidder is expected to examine all instructions, forms, terms, conditions and
specifications in the Bidding Documents, before submission of his bid. Failure to
furnish all information or documentation required by the Bidding Documents may
result in the rejection of such bid.
5.3 Qualifying Requirements, if applicable. The qualifying requirements for the
tender are specified in the NIT/Tender enquiry.
5.4 Documents in support of meeting Qualifying Requirements
Bidders are required to submit documents to satisfactorily establish their meeting
the Qualifying Requirements stipulated in the tender.
Bidders are required to furnish the details of the past experience like authentic
Work Orders/Purchase Orders/Letter of Awards/Contract Agreements, client
certificates, completion certificate, etc. in support of meeting the Qualifying
Requirements based on which selection is to be made as per format. These
references shall only be considered to ascertain the bidder’s compliance to
Qualifying Requirement (QR). No claims without supporting documents shall be
accepted in this regard. Bidders wishing to provide additional Work Orders/Purchase
Orders/Letter of Awards/Contract Agreements are required to declare the same in
similar format which shall be additionally attached in the offer.
5.5 Bid Drawings: The Bidder is requested to refer the Technical Specifications for the
provisions in this regard.
5.6 CLARIFICATION OF BIDDING DOCUMENTS: A prospective Bidder requiring any
clarification of the Bidding Document shall email the query to the concerned
executive at least five days prior to the BOD. EMPLOYER will respond to any request
for clarification or modification of the bidding documents that it receives within the
time line specified. EMPLOYER will upload the Clarifications on www.rgppl.com &
www.ntpctender.com website. Bidders can view these clarifications.
Bidders are advised to regularly check under Clarification/Corrigendum tab
regarding posting of clarification, if any.
Bidders must check the Clarifications issued before submission of Bid. Should the
Employer deem it necessary to amend the Bidding Document as a result of a
clarification, it shall do so and upload the amendments in the tender on the
www.rgppl.com & www.ntpctender.com website.
6. PRE-BID CONFERENCE (If specified in the NIT/Tender Enquiry)
6.1 Employer at its discretion may organize a pre-bid conference with the prospective
Bidders. The purpose of the conference will be to clarify the package related
issues and to respond to the Bidder’s queries, which may arise from the Bidding
Documents, site visit etc. The Employer will give a notice of the pre-bid
conference to the Bidders at least seven (7) days prior to the said pre-bid
conference unless otherwise fixed or informed in the IFB/NIT.
6.2 The Bidders are required to submit their questions/ clarifications/queries etc. in
writing including by way of email from the registered email Id so as to reach the
Employer at least three days before the pre-bid conference. It may not be
practicable at the conference to answer the questions which are received late.
6.3 Record notes of the pre-bid conference including the Employer’s response to the
queries raised by the Bidders in writing may be prepared and transmitted to all
the prospective Bidders by the Employer. Further, any modification to the Bidding
Documents which may become necessary as a result of the pre-bid conference