Page 2 of 5
Corrigendum, if any, shall be done at our eProcurement Portal
(https://eprocurentpc.nic.in/nicgep/app) only.
No Queries from Bidders, whatsoever, shall be entertained by the Employer
beyond the last date of receipt of Queries as specified above.
5.0 All bids must be accompanied by Bid Security for an amount of INR 1,00,000/-
(Indian Rupees One Lac only) in the form as stipulated in the Bidding
documents. Bid Security shall be submitted in a sealed envelope separately in
physical form by the stipulated bid submission closing date and time at the
address given below.
ANY BID NOT ACCOMPANIED BY AN ACCEPTABLE BID SECURITY IN A
SEPARATE SEALED ENVELOPE SHALL BE REJECTED BY THE
EMPLOYER AS BEING NON-RESPONSIVE AND SHALL NOT BE OPENED.
Benefits to MSE- Not applicable for this work.
6.0 QUALIFYING REQUIREMENTS FOR BIDDERS.
The bidder who wishes to participate in the bidding shall meet the Qualifying
Requirements stipulated hereunder:
6.1 Technical Criteria:
The Bidder should have designed, supplied, ‘erected/supervised erection’ and
‘commissioned/supervised commissioning’ of SPV based grid connected power plant
of at least one plant of 25 KWp or above and cumulative capacity of 100 KWp or
above. The reference plant of 25 KWp or above capacity must have been in successful
operation for at least six months prior to the date of techno-commercial bid opening.
Note:
1. The qualifying criteria related to work executed as mentioned in clause 6.1 above
means that the bidder should have achieved the criteria specified above, even if
the total contract is started earlier and/or is not completed/closed.
2. In case of orders under execution, the value of work executed till the date
of techno-commercial bid opening by the client shall be considered acceptable.
3. The reference SPV Based grid connected power plant of 25 KWp or above
capacity developed by Bidder for itself or any other client.
4. Bidder shall submit certificate of successful completion/operation from the
Owner. In case the Bidder has executed the project for its own group
company/special purpose vehicle, Bidder shall, in addition, obtain a certificate
from DISCOM/power procurement agency for commissioning date.
5. Projects executed by Bidder's group company, Holding Company or Subsidiary
Company shall not be considered as Bidder's experience for meeting the QR.
6. The Bidder shall also be considered qualified, in case the award for the reference
works has been received by the Bidder either directly from owner of plant or any
other intermediary organization. A certificate from such owner of plant shall be
required to be furnished by the bidder along with its techno-commercial bid in
support of its claim of meeting requirement stipulated above.
7. SPV based Roof-top and ground mounted solar power projects, which are grid
connected, shall be considered as Bidder's experience for meeting the QR.