
d). Wherever the ash dykes and other embankments are constructed in different contracts,
the height applicable to individual contract only and not the cumulative effect shall be
considered for the purpose of determining compliance of clause 7.1.1. For example,
where the contract is for raising an embankment, only the raising portion shall be
considered and not the earlier starter dyke.
e). In clause 7.1.0 above, the word “executed” means the bidder should have achieved
the criteria specified in the qualifying requirements, within the preceding seven (7)
years period reckoned as on the date of Techno-commercial bid opening, even if the
contract has been started earlier and /or is not completed / closed.
f). In clause 7.1.1 above, bidder should have constructed full 4.0-meter height of
embankment work specified in the qualifying requirements within the preceding seven
(07) years period reckoned as on the date of Techno-commercial bid opening, even if
the contract has been started earlier and/ or is not completed /closed.
g). The “one (1) year period” means any continuous 12 months’ period. However, for
two (2) concurrent works, the same 12 months’ period shall be considered.
h). In case of works stipulated in 7.1.2 above the word “earthwork” shall mean earth
/ash. The quantity of earthwork in filling only will be considered for qualification
i). Reference works executed by the bidder, as a member of Joint Venture / Consortium/
Associate can also be considered provided
1. The allocation of scope of work between the partners of the Joint Venture /
Consortium/ Associate is clearly defined in the executed Joint Venture
agreement/ Consortium Agreement/ Deed of Joint Undertaking and Bidders’
scope of work and break-up of quantities executed by them as individual
contribution in the Joint Venture / Consortium/ Associate, duly authenticated
by the Project Authority; meet the relevant provisions of qualifying
requirement.
2. In case the reference work has been executed by the Bidder in an integrated
Joint Venture wherein allocation of scope of work and break-up of quantities
between the partners is not clearly specified in the integrated Joint Venture
Agreement, then for Clause 7.1.2 above, the credit of executed quantities can
be claimed by the bidder in the ratio of bidder’s share in the integrated Joint
Venture Agreement, provided the bidder establishes that it regularly
undertakes works as at Clause 7.1.2 above.
3. The executed works/ quantities by integrated Joint Venture shall be duly
authenticated by the Project Authority. However, the bidder will not be eligible
to claim the credit of executed work by integrated Joint Venture for Clause
7.1.1 above, unless the bidder has individually executed the work meeting the
requirement of Clause 7.1.1 above and which has been duly authenticated by
the Project Authority.
j). Reference work executed by the bidders as a sub-contractor may also be considered
provided the certificate issued by main contractor is duly certified by Project
Authority specifying the scope of work executed by the sub-contractor in support of
qualifying requirements
k). The word “executed” mentioned in clause 7.1.0 means that the bidder should have
achieved the criteria Specified in clause 7.1.0 with any of the following conditions:
i. Case – I: The work is started earlier (prior to the period stipulated in
clause 7.1.0) but completed within the stipulated period as mentioned in
clause 7.1.0 In such cases, entire executed quantity of the relevant work
vide the work order shall be considered for evaluation.