1.0 NTPC Limited invites online applications from eligible domestic Agencies for the
above mentioned Enlistment. The tentative brief Scope of work is as follows:
The aim of the EIA study is to establish the existing baseline environmental
conditions, predict impacts of the power plant and associated facilities, and
formulate Environmental Management Plan and develop a post study monitoring
programme. The EIA Report is required for conducting Public Hearing by State
Pollution Control Board (SPCB), Environmental Clearance (EC) from Ministry of
Environment, Forest and Climate Change (MOEF&CC) and Consent to Establish
(CTE) from SPCB.
The brief scope of services includes literature review, field studies, impact
assessment and preparation of the EIA documents (Draft EIA Report, Executive
Summary of Draft EIA Report in English and Local Language and
Comprehensive EIA Report etc.) covering the disciplines of Land Use, Water
Use, Demography & Socio-economics, Geology, Soils, Sediments, Hydrology,
Water Quality, Meteorology, Air Quality, Terrestrial Ecology, Aquatic Ecology,
Noise, Risk Assessment, Occupational Health and Safety and Cumulative
Impact Assessment from all sources in study area etc.
The EIA Study/Report is to be undertaken/prepared in accordance with the
provisions of MOEF&CC EIA notifications dated 14.09.2006 and amended
thereof. The EIA Study/ Report needs to be in compliance to the conditions of
Terms of Reference (TOR) as accorded by MOEF&CC for a project.
The consultant will be required to present the findings of the EIA Report before
the Public Hearing meeting, SPCB, Forest Department, Forest Advisory
Committee (FAC), Expert Committee of MOEF&CC and other regulatory
agencies and submit all clarifications/replies to the queries, as and when
required.
The brief scope of work for EIA Studies outlined above is indicative and not
exhaustive. The detailed scope of work for EIA study is finalized for a project