v. To coordinate with vendor for ash handling system for inputs and interface
issues.
vi. Proven principles for mound design & construction to be used giving due
consideration to the local geology, climate & existing area drainage pattern
including conditions that will arise during the monsoon period.
vii. Stability and seepage analysis to be performed through appropriate method.
Analysis to be performed for both static & seismic conditions. Appropriate
safety factors to be ensured for the intermediate and ultimate height of ash
mound.
viii. Design of ash mound & the methodology proposed for its construction should
ensure stability of the mound at all times and ensure that pollution of the
atmosphere and ground water is minimized. Liner if required shall specify
suitable material.
ix. Appropriate drainage design to be provided for surface water runoff to
prevent pollution of adjacent natural drains/river and ground water. The slope
drain shall be provided with energy dissipater’s.
x. Ash mound design and its proposed methodology of construction to be
flexible as to allow the ash to be handled in all circumstances that are likely to
arise from climatic conditions, plant malfunction and different rates of ash
production. It shall ensure measures for control of fugitive dust both at
intermediate stages & final completion of ash mound.
xi. The design and proposed construction methodology for ash mound and civil
works to be done as per latest Indian Standards. Where a relevant Indian
Standard does not exist British, American, German or any other standard
may be used.
xii. To furnish appropriate landscape design for final surfaces of the ash mound
furnishing the recommended plant species to be planted on the surface to
provide protection and stability and good aesthetic look considering that the
ash mound is to be retained as a natural feature in the area during the life of
plant (25 years) and thereafter. Provision for a trial planting area and plant
nursery within the mound site shall be kept.
xiii. Methodology for safe extraction of ash directly from mound by users. It is
envisaged that there will be off take of ash from the mound in trucks/bulkers
for use by the industry. The same shall be considered in the design and
scheme & methodology for safe off take of the ash from mound for
prospective users, shall be furnished.
xiv. Design of all ancillary buildings like control and MCC/ switchgear buildings,
administrative building, pump houses, safety centre, rest rooms with drinking
water facilities, laboratory building, workshop etc. shall be provided for
regular servicing of plant & equipment working on the mound and for the
welfare and control of the personnel involved.
xv. The ash handling plant and proposed method of construction of the ash
mound shall be designed to control & minimize the extent of fugitive dust
emissions. The main area of likely dust nuisance are the belt conveyors, ash
moving equipment, Temporary & emergency yards, site traffic, wind erosion
etc. including the ash mound construction / operation stage. A
comprehensive dust control system/ scheme shall be provided.
xvi. To design Ash mound, the following Mechanical & associated works are also
to be included in DPR:
All plant & equipment/ machines like conveyors (fixed, shiftable and
extendable or any other technology), boom spreaders, Stackers/
Reclaimers, dust suppression system, drainage pumps etc. required for
the development of ash mound including their number and capacities.