(iii) “Flue Gas Desulphurisation System” or “FGD System” wherever appearing above shall
mean consisting of at least Absorber System.
(iv) The word “executed” in Clause 1.3.1 (b)/ Clause 1.3.1 (c) means the Bidder should have
commissioned the project(s) specified in the Clause 1.3.1 (b)/ Clause 1.3.1 (c) even if
the contract has been started earlier and / or is not completed / closed.
(2) Erection/Commissioning
Where erection / supervision of erection and commissioning / supervision of
commissioning has not been in the scope of the Bidder as mentioned in clause 1.1.1,
1.2.1 & 1.3.1 (a), the Bidder should have acted as an advisor for erection and
commissioning. Necessary documents / certificates from the client, in support of above
shall be furnished along with the Techno-Commercial bid.
(3) Direct / Indirect order
The Bidder/ QFGDM shall also be considered qualified, in case the award for executing
the reference works has been received by the Bidder/ QFGDM either directly from
owner of plant or any other intermediary organization. However, a certificate from such
owner of plant or any other intermediary organisation shall be required to be furnished
by the Bidder along with its Techno-Commercial bid in support of the Bidder's/ QFGDM
claim of meeting the qualification requirement as per clause 1.1.1, 1.2.1, 1.3.1(a) &
1.4.1 above. Further, certificate from owner of the plant shall also be furnished by the
Bidder along with the Techno-Commercial bid for the successful operation as specified
at clause 1.1.1, 1.2.1, 1.3.1(a) & 1.4.1 above.
(4) Holding Company as a Qualified Wet Limestone based Flue Gas Desulphurisation
system Manufacturer
(i) A Holding Company, singularly or collectively along with its Subsidiaries (held either
directly or indirectly), meeting the requirements of clause 1.1.1 above shall also be
considered as QFGDM.
(ii) In such a case, if the Holding Company itself is not the Bidder as a QFGDM, the Holding
Company and all such subsidiaries lending strength / experience to the Holding
Company for meeting the requirements of clause 1.1.1 above should necessarily be part
of the DJU being submitted by the Bidder for successful performance of the contract as
per format enclosed with the bidding documents, failing which the bidder shall be
disqualified and its bid rejected. Further, the Holding Company and all such entities
lending strength / experience to the Holding Company for meeting the requirements of
clause 1.1.1 above shall each be required to furnish separate on demand bank
guarantees as per the format enclosed with the bidding documents for an amount
aggregating 5 % of the total contract price of the Flue Gas Desulphurisation System
Package for the awarded project divided equally among them, in addition to the contract
performance security to be furnished by the Bidder. This bank guarantee requirement
shall supersede bank guarantee requirement stipulated at clause 1.2.4, 1.3.4 & 1.4.4 for
the QFGDM.
(iii) In case the Holding Company itself is the Bidder as a QFGDM as per clause 1.1.1, the
Holding Company shall submit its board resolution stating that in case of any likely
change of management control of any of these subsidiaries lending strength/ experience
to the Holding Company for meeting the requirements of clause 1.1.1 above , the Bidder
shall arrange for separate on demand bank guarantees as per the format enclosed with