DETAILED INVITATION FOR BID
Battery Energy Storage System for 17 MW Solar PV Project at
Manglutan in South Andaman, A&N Islands
BIDDING DOCUMENT NO.: RE-CS-5728-004(B)-9
SECTION-I (IFB)
PAGE
1 OF 8
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
RENEWABLE ENERGY – CONTRACTS SERVICES, NOIDA.
DETAILED INVITATION FOR BIDS (IFB)
FOR
BATTERY ENERGY STORAGE SYSTEM FOR 17 MW SOLAR PV PROJECT AT MANGLUTAN
IN SOUTH ANDAMAN, A&N ISLANDS
(International Competitive Bidding)
IFB No.: 40073898 Date: 05.05.2017
Bidding Document No: RE-CS-5728-004(B)-9
1.0 NTPC invites online bids from eligible bidders in TWO STAGES (i.e. Stage-I: Techno-
Commercial Bid and Stage-II: Price Bid) from eligible bidders for Battery Energy Storage
System for 17 MW Solar PV Project at Manglutan in South Andaman, A&N Islands as
per the scope of work briefly mentioned hereinafter.
2.0 BRIEF SCOPE OF WORK
The scope shall cover Design, Engineering, Supply, Packaging and Forwarding, Transportation,
Unloading, Storage, Installation, Testing, Commissioning, Grid Integration with 17 MW Solar PV Plant
and 33 kV grid, of 6 MW, 24 MWh (at 33KV output throughout life of 25 Years) Battery Energy
Storage System (BESS, PCU, Transformers, BMS, EMS, Switchgears, Cables, Illumination, SCADA,
weather prediction system, fire detection system, 33KV Metering Station etc. required for smooth
operation) including twenty five year Operation and Maintenance (O&M) works on turnkey basis.
Bidder shall provide comprehensive operation & maintenance of the grid connected BESS System for
a period of twenty-five (25) years from the date of successful completion of trial run. Bidder shall be
responsible for identifying and providing any and all the other additional equipment, component and
services necessary for its integration with the existing ac systems, as a fully functional grid interactive
BESS System. All equipment, materials and services that are necessary for the satisfactory operation
of the BESS for entire O&M period of 25 years shall be deemed to be included in the scope of EPC
package work and shall not be limited to the following:
The scope includes the following:
1. Design, fabricate, ship, assemble, test, start-up, commission of all the equipment and system(s)
including civil works, warrant and make ready for service a fully functional turnkey battery energy
storage system that meets or exceeds all requirements delineated herein up to the battery energy
storage system.
2. All Civil, Structural and Architectural works including construction facilities and construction power
Distribution.
3. Design, install and make ready for the electrical connections from the battery energy storage system
to the 33 kV system.
4. Design, install and make ready a battery management system with control and communication system
for monitoring and controlling battery and PCU parameters and the communication connection from
the battery energy storage system of other projects of NTPC and the substations of A&N distribution
network.