NTPC Limited
(A Government of India Enterprise)
Feroz Gandhi Unchahar Thermal
NOTICE INVITING TENDER (NIT)
FOR
Supply, Erection, Testing & Commissioning of 6.6KV single CKT HT line for Umran Ash Dayk. (PKG NO- 035/2085)
(Domestic Competitive Bidding)
NIT No: 40026865 |
Date:23.09.2014 |
Bidding Document No: |
035/2085 |
1.0 NTPC invites
2.0 |
Brief Details |
|
NIT No. |
40026865 |
|
NIT Date |
23.09.2014 |
|
Document Sale Commencement Date & Time |
23.09.2014 10:00:00 |
|
Document Sale Close Date & Time |
15.10.2014 17:30:00 |
|
Source of IFB/NIT |
Feroz Gandhi Unchahar Thermal |
|
Contract Classification |
Works Contract |
|
Last Date and Time for Bid submission |
31.10.2014 13:00:00 |
|
Technical Opening Date & Time |
31.10.2014 15:00:00 |
|
Bid Opening Date & Time |
31.10.2014 15:00:00 |
|
Cost of Bidding Documents in INR |
1,300.00 |
|
EMD in INR |
27000.00 |
|
|
||
Last |
Query Date (if any) |
|
3.0Bid Security and Integrity Pact (if applicable) shall be submitted in a sealed envelope separately offline by the
stipulated bid |
submission closing |
date and time at the address given below. Any bid without an acceptable Bid Security |
and Integrity |
Pact (if applicable) |
shall be treated as |
4.0 A complete set of Bidding Documents may be downloaded by any interested Bidder on payment
(https://etender.ntpclakshya.co.in/sap/bc/gui/sap/its/bbpstart). For logging on to the SRM Site, the |
bidder would require |
||
vendor code and SRM user id and password which can be obtained |
by submitting a questionnaire |
available at our SRM |
|
site as well as at NTPC tender site (www.ntpctender.com). First time users not |
allotted any vendor code are required to |
||
approach NTPC at least three working days prior to Document Sale |
Close date |
alongwith duly filled in questionnare for |
|
issue of vendor code and SRM user id/password. |
|
|
|
5.0Brief Scope of Work & other specific detail
Scope of work:
The scope of work shall include:
a) Design, engineering, preparation of necessary drawings, supply, transportation, handling, fabrication, painting, installation, testing and commissioning of 6.6KV line and its associated equipments from Umaran pump
Umaran Ash dyke. |
|
|
|
|
|
|
|
|
|
|
b) The transportation of owner issued material from central store/ the place advised by the |
EIC |
to |
the work place |
|||||||
including loading and unloading shall also |
be |
under the scope of the bidder. |
|
|
|
|
|
|
||
c) Preparation of quality plan for all items |
as per |
the |
technical specifications in |
consultation |
with |
the |
EIC |
and it's |
||
approval by our FQA department. |
|
|
|
|
|
|
|
|
|
|
d) The storage facility for the equipments |
procured by |
the |
vendor/issued by NTPC at |
a suitable |
location |
for |
safe |
custody |
||
of the material till the completion of the erection work. The responsibility of safety and security of man and material lies with the agency.
Technical Specifications: |
|
|
|
|
|
|
S/E of 40mm dia, 3m long MS earthing rod: |
|
|
|
|
||
The 40 mm dia MS rod |
shall be pointed at one end and pushed directly into the ground. In other end, suitable |
|||||
connecting lug shall be welded for bolting the earth strip. |
|
|
|
|
||
a) Every alternate pole has |
to be earthed with the help of GI strip (size 25x6mm) connected between MS electrode and |
|||||
the rail pole. The GI strip |
shall be welded/bolted with earth electrode and bolted/welded with the rail pole. |
|
||||
b) The welded joint shall |
be |
painted with |
Slag should be |
removed |
before |
applying |
|
|
|
|
|
|
|
c) The |
be |
embedded in cement concrete of pole |
above ground |
level as |
per |
the site |
requirements/instructions of |
the |
|
|
|
|
|
d) No extra payment will be made for any fabrication work.
U/G Laying of XLPE HT cable 3C*150 sqmm
a)A layer of 8cm sand shall be provided before laying the cable as sand cushioning and 17cm of sand shall be provided above cable before placing the protective covering of bricks.
b)The cable should be tested before laying it.
c) |
At the time |
of installation, aprrox. 3m of surplus cable shall be left on ech terminal end of the cable and each side |
of |
underground |
joints. |
d)The width and depth of the trench shall be 35cm and 120cm respectively. |
||
6.6KV Cable upto 400 sqmm Laying in Pipe |
||
a) |
Cable shall |
be laid in suitable size of GI/CI pipe across the road and pool. |
b)Both ends of pipe should be grouted.
c)Cable grips/draw wires, winches etc. may be employed for drawing cable trough pipes.
e) All MS |
components used |
in fixing the cable shall be either hot dip galvanised or given 2 coats of |
and finished |
with 2 coats of |
approved Al paint. |
S/M HT cable end termination (outdoor) and S/M HT cable end termination (indoor)
a)The Raychem make heat shrinkable cable jointing kit shall be procured by the agency for jointing.
b) Before jointing is commenced all safety precautions like isolation, discharging, earthing, display of caution board at the
location |
shall |
be ensured. |
|
c) |
The |
cable |
end shall be prepared before end termination as per the instruction manual. |
d) |
cable end |
termination done by experienced cable jointer. |
|
S/E 11 kV stay set(19/20mm dia)
a) Supplying and erection of galvanized stay set for 6.6kV
7/4.00mm dia GI stay wire and 6.6kV strain insulator etc in cement |
concrete 1:3:6(1 cement:3 coarse sand: 6 graded |
|||||||
stone aggregate 40mm nominal size) foundation of size 0.28 cub. |
metre |
including |
excavation |
and refilling |
etc. as |
|||
required. |
|
|
|
|
|
|
|
|
b) |
|
|
|
|||||
c) Gay starin insulator shall be |
fixed at the middle of the |
be C type. |
|
|
||||
d) The |
|
|
|
|
|
|||
Erec. of rail |
|
|
|
|
|
|
|
|
a) The rail pole shall be correctly aligned |
after excavation and PCC but |
before concreting or |
||||||
b) Pole shuttering shall be round in shape of 600 mm dia. and 2.0 m high. |
|
|
|
|
|
|||
c) Before applying |
by |
brushing |
using steel |
brush. After |
2 coats |
|||
of primer, 2 coats of branded |
Aluminum |
paint should be given. |
|
|
|
|
|
|
d)black bitumen paint shall be |
applied on |
rail pole at bottom portion up |
to two |
meter prior grouting. |
|
|||
e)The loading of poles shall be done only after 1 weeks of proper curing so that failure of foundation shall be avoided. S/E of 6.6kV disc insulators
a)The disc insulator fitting should standard size with rated voltage=12 kV rms, impulse withstand voltage=75kV rms, wet
power frequency withstand voltage=35kV rms and minimum creepage distance=320mm. |
||||
b)Porcelain |
used in insulators should be homogenous and free from cavities and other imperfections. |
|||
c) All iron parts should be |
||||
S/E of 6.6kV pin insulators |
||||
a) |
The |
disc |
insulator fitting should standard size. Porcelain used in insulators should be homogenous and free from |
|
cavities |
and |
other imperfections. |
||
b) |
Glazing |
of |
porcelain shall be uniform brown colour, free from blisters, burns and similar defects. |
|
c) |
Insulators |
shall be suitable for heavily polluted atmosphere. Rated voltage=12 kV rms, impulse withstand |
||
voltage=75kV rms, wet power frequency withstand voltage=35kV rms and minimum creepage distance=320mm. |
||||
S/E of |
6.6kV |
lightning arrestors |
||
a) The 6.6KV lightening arrestor shall be employed with each phase at terminals and any other places where specified depending on the local climatic conditions. These shall be mounted on suitable brackets.
b) Suitable earth connections should be provided as per rules. These devices should be connected ahead of fuses(if any) c) An independent earth electrode needs to be provided for each LA. The earth lead (25*5mm GI flat) from the earth electrode to LA should be a continuous and fixed structure insulated with the support structure to avoid multi contacts.
Supply and erection of pole top brackets(75*40mm)
&
Supply and erection of V
a)Supplying and erection of channel iron 75*40 sqmm *7.14 kg per metre pole top bracket for single 11kV overhead line conductor complete with 50mm*6mm flat iron clamps, bolts and nuts etc and painting with primer and finish paint with 2
coats of Al paint of standard make. |
|
|
|
b)Supplying of channel iron 75*40 sqmm *7.14 kg |
per metre |
2 11kV overhead line conductors complete |
|
with 50*50*6 cu. mm angle iron bracket welded |
to the channel iron and complete with 50*6 sq. mm MS flat iron |
||
clamps, |
bolts and nuts including drilling holes for |
insulator pins, bolts and |
nuts etc and painting with primer and finish |
paint as |
required. |
|
|
c)For the proper erection of
Erec. of ACSR conductors(7/3.35mm)( ERCON3.35):
a) Stringing of conductors: Care should be taken while handling ACSR conductors because of its relative softness.
b)The conductor drum should be rotated in the direction of arrow marked on it to avoid damage of conductor. Appropriate tools should be used for the same.
c)During stringing, the standard sag table or chart shall be followed. No kinks should come in any conductor.
d)Binding of conductors: Binding of conductors to insulators shall be sufficiently firm and tight to ensure that no intermittent contacts develop.
e)Jumpers: Jumpers shall be neat and symmetrical to the run of the conductor. These shall be so made as to prevent
occurrence |
of fault due |
to wind or birds. They should be of same material as the line current conductor and have |
|
adequate |
current carrying |
capacity. |
|
P/F of 25*5 sqmm GI earth strip |
|||
a) The earth strip shall |
be connected between earth electrodes and rail poles/structures and welded with earth electrode. |
||
The other |
end shall be |
fixed with rail poles/structures through nuts and bolts. |
|
b) After |
removal of slags from welded joints, |
||
each) to |
prevent rust. |
|
|
c)The welded joints should have proper Lap length.
d)25*5 mm GI clamps should be used for clamping GI strip with structure/pole at and interval of 1.5 mtrs and on both sides of the bends in addition to the straight run.
I,T&C of 11kV
Installation, testing and commissioning of GO/DO fuse:
a) The height of operating handle for GO switch shall be about 1.3m above ground level. The stopper locking facility in off/on positions should be such that it doesn#t open/close by gravity etc.
S&F of HT danger plate(250*200 sqmm) |
|
|
|
a) All supports carrying HT |
line shall be fitted with danger plates as |
per IS:2551 (With latest |
amendments) at the height |
of 3 metres from ground. The voltage level of line shall be mentioned on the board. |
|
||
b) The danger notice board should be bilingual. (Hindi and English) |
|
|
|
c) The notice board shall be |
firmly fixed with the support structure/rail pole with the help of |
2 nos. of clamps made of |
|
25*3 mm GI strip including |
S/F of hot dip galvanized nuts, bolts and |
washers. |
|
S&F of
Supply, |
carriage |
and |
fixing of |
the |
elevation of |
3m |
from |
the |
ground, the |
|
pole in 1.5m depth and |
||||||||||
clamped |
at both |
ends |
by suitable |
MS clamp fixed on the pole. The nuts, |
bolts |
and washers |
shall |
be hot |
dip |
galvanized. |
GI earth plate electrode (600*600*6 mm thick):
a) Earthing with GI earth plate 600*600*6 mm including accessories and providing masonry enclosure with cover plate
having locking |
arrangement and watering |
pipe |
etc. ( with charcoal or coke and salt) as required should be done around |
|
the |
transformer. |
|
|
|
b) |
Proper testing |
of earth resistance value |
shall |
be carried out. |
S&F of cradle type cage guard:
a) The cage guard shall be installed between pole to pole across the road , bridge, canal and pathway crossing carried by same pole supported by 50*50*5 mm MS angle fixed with the help of suitable clamp on pole.
b)Minimum 9 nos. of cage laces shall be provided in each span. The guard wire shall be firmly bonded with the earth wire laid on the top of the pole.
c)Guard wire shall run, not less than 30cm beyond the outermost bare conductor of the configuration in case of 6.6kV lines. The guard wire shall be suitably clamped with support angle at each span.
LT cable laying in open duct
a) Cable shall |
be laid in a suitable manner ensuring continuity all |
through |
the |
line. |
|
b) All MS components used |
in fixing the cable should be either hot dip galvanized or given 2 coats of |
||||
and finished |
with 2 coats of |
approved Aluminum paint. Fasteners |
shall be |
of |
GI. |
LT cable end termination 3*70 sqmm
a)Before jointing is commenced all safety precautions like isolation, discharging, earthing, display of caution board at the location shall be ensured.
b)The kit for making joint will be issued by NTPC. The cable end shall be prepared before end termination as per the instruction manual.
Structural steel work in single section
a) MS steel shall |
be provided by NTPC but fabrication of steel structures (support structures of LA, GO, DO, |
transformer supports if required, LT MCC channel supports etc.) shall be done by the agency. |
|
b) All bolts, nuts and washers shall be |
|
Installation, testing |
and commissioning of transformer |
The 6.6/.0415kV 500/630 kVA distribution transformer shall be transported from store to installation site. Placing the
transformer on foundation /structure as the case may be, shall also be carried out |
by the agency. Testing & |
|||||||||||
commissioning shall be carried out by the agency |
however Testing equipments shall be made available |
by |
NTPC on |
free |
||||||||
of cost basis. The shifting of testing equipments |
to |
the location and returning back |
to |
the |
electrical lab shall be under |
|||||||
the scope of agency. The testing of transformer after installation shall be done prior to charging. |
|
|
|
|
|
|||||||
Installation, testing and commissioning of 415V LT MCC |
|
|
|
|
|
|
|
|
||||
Loading ,transportation, unloading ,placing on trench foundation, alignment, tagging |
with |
support |
channels, |
cleaning, |
||||||||
testing and commissioning of LT MCC as per the site requirement and instruction of |
engineer in |
charge |
shall |
be carried |
||||||||
out by the agency. The necessary testing equipments shall be made available by NTPC |
free of cost. However, the |
|||||||||||
shifting to |
the location from the electrical |
lab & |
returning back shall be under the scope of |
agency. |
|
|
|
|
||||
|
Supply, Installation, testing and commissioning of DOL starter |
|
|
|
|
|
|
|
|
|||
The tech. |
specification of DOL starter |
should |
be |
matching with the specification |
mentioned |
against |
the |
item. |
The |
|||
installation of DOL |
Starter on the wall/steel structure shall be carried out by agency. Necessary testing, |
|||||
connections/interconnections shall be carried out by the |
agency. Fabrication, grouting |
of frame at wall, & |
repairing |
of |
||
wall is in scope of agency. |
|
|
|
|
||
Terms and Conditions |
of |
the Contract |
|
|
|
|
1.Bidder shall bring all |
T & Ps required for erection, |
testing and commissioning of |
6.6kv overhead single |
circuit |
HT |
|
line, DOL starter and other associated equipments(The testing equipments required for transformer & LT MCC shall be provided by NTPC).The list of T&Ps shall be submitted to IEC before start of work for review.
2.The list of major bought out items along with make etc. shall be prepared and submitted to IEC for approval before procurement. All materials under supply scope of agency shall be standard and NTPC approved.
3.The bought out items shall be inspected and accepted by NTPC before use at site. The test certificate of all major procured items shall be submitted by agency at the time of inspection for review and acceptance.
4.Since the 6.6kv HT line shall be installed outside plant boundary along the discharge channel upto the Umaran Ash Dyke, so due care shall be taken while executing electrical works like stringing, charging etc. The work place shall be cordoned off and danger tags placed. Specially when excavation, pole hoisting etc. is going on.
5.Since |
the |
work place is outside the plant boundary, the arrangement of the construction power and construction water |
shall be |
the |
responsibility of the agency. However, three phase construction power supply connection will be provided |
near Umaran P/H.
6.The construction work of HT line should not damage the existing ash pipelines/discharge channel bunds and also it shouldn't obstruct vehicular movement near the work place.
7.The permission/clearance for the 6.6kV overhead line crossings where ever required shall be obtained by the agency.
ACSR conductors,GO,DO,3 core*150sq.mm HT cable etc shall be issued free of cost for execution |
|
from NTPC central |
stores. The agency has to arrange it's own transportation for shifting from NTPC central store/site |
to |
|
9.The contract value shall be firm and no escalation will be allowed in any circumstances.
10.The drawings attached are for the tender purpose only. The bidder shall prepare all necessary drawings required for execution of work and same shall be submitted for approval before the start of work.
11.The MS steel used for fabrication work shall be issued by |
NTPC free of cost, how ever the transportation shall be in |
the scope of agency. |
|
12.The time is of essence for the work. Power Supply shall |
be made available in time for commissioning of discharge |
water pumps. Hence, the work shall be completed within stipulated time period. |
|
13.Defect liability period shall be 12 months from the date of |
completion of work. |
14.The cement, Concrete, sand/morng(1:3:6) required for completion of work shall be in contractor's scope.
15.Agency shall maintain the record of material which shall be issued by NTPC free of cost and balance material after completion of work shall be returned back to the central store through MRN.
16.The agency has to submit the organisation chart of deployed manpower before the start of work.
17.All the PPEs adequate in number should be made available at the site for the safety of the workers.
18.The agency should submit workman compensation insurance policy to the EIC before commencement of the work.
19.The work shall be carried out as per IE rules,latest revised IS codes and CPWD specifications.
20.The work shall be carried out as per regulation and in best |
workmanship. |
The supervision of the work shall be |
carried out by experienced executives of agency. |
|
|
21.The pole span and the clearance shall be decided as per the site |
conditions/IE |
rules. |
22.The necessary documentation for the billable items shall be maintained and the original invoices shall be submitted to the EIC.
23.The agency will have to prepare a L2 schedule in consultation with the EIC for the timely completion of the work. Weekly and monthly progress report of the work shall be submitted to the EIC.
24.GCC of the NTPC shall be applicable for the work.
25.The wage payment to all daily wage workers shall be made |
in the first week of every month as per minimum wages |
||||
act |
and |
necessary |
record shall |
be maintained and submitted to |
the EIC. |
26. |
All |
statutory |
laws, labour |
laws, PF laws, labour insurace |
policies shall be complied by agency and no any extra |
payment shall be made on account of implementation of above requirements.
27.The contractor should have electrical #A# class Licenses issued by Govt. authority valid on date of bid on date of bid opening..
28.Completion period:- Completion period of the contract:06 months from the date of start of the work.
29.Defect liability period: The defect liability period shall be 12 months reckoned from the date of commissioning of the system.
30. Payment Terms- Progressive payment |
@90% of executed value shall be paid against |
completed work through RA |
||
Bills. Balance 10 % shall be payable after |
successful Testing and commissioning of work. |
|
||
31. Agency shall watch & ward the infrastructure developed by them till the handing over. |
|
|||
For free issue material, the agency has |
to submit Indemnity Bond of |
appropriate value in favour of NTPC in NTPC |
||
prescribed format. In case of theft / loss |
of such material, recovery shall |
be made @ twice |
the value of material. |
|
32. Security Deposit: SD @10% shall be deducted from the running bill of agency limited to 10% of Contract Value.SD amount will only be released after successful completion of Defect Liability period. However, the same may be released on submission of PBG of equivalent amount in favour of NTPC in NTPC format.
FREE ISSUE ITEMS |
|
|
|
|
|
S.NO. |
DESCRIPTION OF MATERIAL |
|
UNIT |
QTY |
|
1 |
XLPE CABLE 6.6 KV GRADE 3Cx150MM2 |
|
MTR |
600 |
|
2 |
XLPE/PVC LT CABLE |
3.5Cx240MM2 |
|
MTR |
250 |
3 |
XLPE/PVC LT CABLE |
3Cx70MM2 |
|
MTR |
300 |
4 |
CONTROL CABLE 7Cx1.5MM2 |
|
MTR |
300 |
|
5 |
RAIL POLE (10 to 12mtr) |
NO |
80 |
|
|
6 |
ACSR CONDUCTOR |
(7/3.35MM) |
|
KG |
2700 |
7 |
GO SWICTH/DO FUSE |
|
NO |
2 |
|
8 |
6.6/0.4KV,TRANSFORMER |
|
NO |
1 |
|
9 |
415 VOLT LT MCC |
|
NO |
1 |
|
10 |
STRUCTURAL STEEL |
|
|
KG |
500 |
6.0 Prospective bidders from U.P. State are compulsorily required to provide TIN number at the time of purchase of
bidding documents. |
||
7.0 |
|
Qualifying Requirements for Bidders: |
7.0 |
Qualifying Requirements: |
|
a)The |
bidder should have the experience of successfully executing the work of erection/ maintenance of HT Line of 6.6 |
|
KV |
or |
higher rating. |
b)The bidder should have executed the similar work ( as per para 7(a)) during last seven (7) years ending last day of the month previous to one in which bids are opened as any of the following :-
(i) One |
similar |
executed |
work |
of |
value |
not |
less |
than |
Rs 10.50 lacs. |
|
|
|
|
|
|
|
|
|
|
|
OR |
(ii)Two |
similar |
executed |
works |
of |
value |
not |
less |
than |
Rs. 6.50 lacs each. |
|
|
|
|
|
|
|
|
|
|
|
OR |
(iii) Three similar executed works |
|
of value not less than Rs. 5.50 lacs each. |
||||||||
c) The |
average |
annual |
turnover |
of the bidder in the three preceding completed financial years, as on the date of bid |
||||||
opening |
shall not be less |
than |
Rs. |
26.50 lacs. |
|
|
||||
8.0Issuance of Bidding Documents to any bidder shall not construe that bidder is considered qualified.
9.0NTPC reserves the right to reject any or all bids or cancel/withdraw the NIT for the subject package without
assigning any reason whatsoever and in such case no bidder/intending bidder shall have any claim arising out of such action.
10.0 Address for Communication
(1)
L D SINGH
SR. MANAGER (CS)
MOB
(2)
VIKRAM PANDEY MANAGER (IT)
Websites: https://etender.ntpclakshya.co.in/sap/bc/gui/sap/its/bbpstart or www.ntpctender.com or www.ntpc.co.in