(A Government of India Enterprise)
FOR
NOTICE INVITING TENDER (NIT)
Auraiya Gas Power Station
NTPC Limited
Supply, Installation and commissioning of Continuous Stack Emission Monitoring System (CEMS) at NTPC
Date:01.09.2014
Auraiya Gas Power Station
Bidding Document No: AUGPS-C
1.0
NIT No: 40025323
2.0
NTPC invites on-line bids from eligible Bidders for aforesaid package, as per the scope of work briefly mentioned hereinafter:
NIT Date
(Domestic Competitive Bidding)
Document Sale Commencement Date & Time
Brief Details
22.09.2014 17:00:00
Source of IFB/NIT
Document Sale Close Date & Time
Last Date and Time for Bid submission
01.09.2014
40025323
02.09.2014 08:00:00
NIT No.
Last Query Date (if any)
Bid Opening Date & Time
Pre-Bid Conference Date & Time (if any)
30.09.2014
EMD in INR
Technical Opening Date & Time
10.10.2014 11:30:00
Auraiya Gas Power Station
10.10.2014 10:00:00
Contract Classification
10.10.2014 11:25:00
Equipment Supply & AMC
105000.00
Cost of Bidding Documents in INR
1,125.00
4.0
A complete set of Bidding Documents may be downloaded by any interested Bidder on payment (non-refundable) of the cost of
Bid Security and Integrity Pact (if applicable) shall be submitted in a sealed envelope separately offline by the stipulated bid
the documents as mentioned above in the form of a crossed account Payee demand draft in favour of NTPC Ltd., Payable at Not
allotted any vendor code are required to approach NTPC at least three working days prior to Document Sale Close date alongwith duly
3.0
Given. or directly through the payment gateway at our SRM Site (https://etender.ntpclakshya.co.in/sap/bc/gui/sap/its/bbpstart). For
submission closing date and time at the address given below. Any bid without an acceptable Bid Security and Integrity Pact (if
applicable) shall be treated as non-responsive by the employer and shall not be opened.
submitting a questionnaire available at our SRM site as well as at NTPC tender site (
www.ntpctender.com). First time users not
filled in questionnare for issue of vendor code and SRM user id/password.
logging on to the SRM Site, the bidder would require vendor code and SRM user id and password which can be obtained by
6.0
Prospective bidders from U.P. State are compulsorily required to provide TIN number at the time of purchase of bidding
documents.
7.0
Qualifying Requirements for Bidders:
Stack Emission Monitoring system(NOx or Sox or any other Particulate Emissions ) and this installation should have been in
Name of work: Supply, Installation and commissioning of Continuous Stack Emission Monitoring System (CEMS) at NTPC Auraiya
5.0
Brief Scope of Work & other specific detail
Station
Supply, Installation and commissioning of Continuous Stack Emission Monitoring System (CEMS) at NTPC Auraiya Gas Power
Gas Power Station.
1. The qualifying requirement for the bidder is stipulated hereunder:
(i) The bidder must have successfully executed the works of supply, installation and commissioning of continuous Stack Emission
# Three(3),orders each of contract value not less than Indian Rupees 20.82 lacs
# Two(2) orders, each of contract value not less than Indian Rupees 26.02 lacs
# Single (1) order of contract value not less than Indian Rupees 41.64 lacs
continuous successful operation for atleast One (1) years as on date of bid opening.
(2) Financial Criteria
(i)The bidder should have supplied, installed and commissioned two (2) Nos (One each at two different Installations) of continuous
Monitoring System any time during last 7 years meeting any one of following criteria as on date of bid opening.
8.0
# NTPC has right to assess the capability & capacity of the bidder.
NTPC reserves the right to reject any or all bids or cancel/withdraw the NIT for the subject package without assigning any
9.0
reason whatsoever and in such case no bidder/intending bidder shall have any claim arising out of such action.
practicing chartered Accountant shall also be considered acceptable.
Issuance of Bidding Documents to any bidder shall not construe that bidder is considered qualified.
completed/ closed.
not be less than Indian Rupees 78.08 lacs
(ii) The average annual turnover of the bidder for the preceding three (03) completed financial years as on date of bid opening shall
# In case where audited results for the last preceding financial year are not available, certification of financial statements from a
# Party has to submit all the documentary evidence in support of above requirement
Note:
# The word #Executed# means that the bidder should have achieved the progress specified in the QR even if the total contract is not
Address for Communication
10.0
PH: +915683-282382/282306
AGM (C&M)
AURAIYA GAS POWER STATION,
FAX:- +915683-282492/282341,
NTPC LTD.
DISTT. AURAIYA # 206244 (U.P.) INDIA.
P.O. DIBIYAPUR,