NTPC invites on-line bids from eligible Bidders for aforesaid package, as per the scope of work briefly mentioned
1.0
NIT No: 40020306
2.0
SUPPLY OF LT POWER CABLES FOR STAGE-II(3*500 MW)& STAGE-III (1*500 MW) LT DRIVES.
Brief Details
Date:21.05.2014
21.05.2014
(Domestic Competitive Bidding)
(11 ITEMS)
Source of IFB/NIT
Contract Classification
Last Date and Time for Bid submission
04.07.2014 10:00:00
Korba Super Thermal Power
Admn. Works & Purchase
Document Sale Close Date & Time
Document Sale Commencement Date & Time
NIT No.
40020306
10:47:46
05.06.2014 17:30:00
NIT Date
21.05.2014
Cost of Bidding Documents in INR
Bid Opening Date & Time
stipulated bid submission closing date and time at the address given below. Any bid without an acceptable Bid Security
3.0
Bid Security and Integrity Pact (if applicable) shall be submitted in a sealed envelope separately offline by the
Technical Opening Date & Time
Last Query Date (if any)
20.06.2014
23.07.2014 10:30:00
1,170.00
EMD in INR
04.07.2014 17:30:00
115000.00
Pre-Bid Conference Date & Time (if any)
and Integrity Pact (if applicable) shall be treated as non-responsive by the employer and shall not be opened.
4.0
A complete set of Bidding Documents may be downloaded by any interested Bidder on payment (non-refundable) of
the cost of the documents as mentioned above in the form of a crossed account Payee demand draft in favour of NTPC
Ltd.,
at
Payable
or
KORBA
directly
through
the
payment
gateway
at
our
SRM
Site
(https://etender.ntpclakshya.co.in/sap/bc/gui/sap/its/bbpstart). For logging on to the SRM Site, the bidder would require
vendor code and SRM user id and password which can be obtained by submitting a questionnaire available at our SRM
site as well as at NTPC tender site (www.ntpctender.com). First time users not allotted any vendor code are required to
approach NTPC at least three working days prior to Document Sale Close date alongwith duly filled in questionnare for
issue of vendor code and SRM user id/password.

Prospective bidders from U.P. State are compulsorily required to provide TIN number at the time of purchase of
bidding documents.
or higher grade and should meet any one of the following criteria, for the above, during the last Seven (07) years ending
6.0
7.0
Qualifying Requirements for Bidders:
1. The bidder should have manufacturer and supplied XLPE insulated flame retardant low smoke power cable of 1.1 KV
5.0
Brief Scope of Work & other specific detail
SUPPLY OF LT POWER CABLES FOR STAGE-II(3*500 MW)& STAGE-III (1*500 MW) LT DRIVES. (11 ITEMS)
b) Two order of value not less than Rs. 29 Lakh [Rupees Twenty Nine Lakh] each.
or
of publication of NIT, the value of the executed till such date will be considered the same is certified by the employer.
c) Three orders of Value not less than Rs. 23 Lakh [Rupees Twenty Three Lakh] each.
with the last date of the month preceding the month of publication of NIT:
a) Single order of value not less than Rs. 46 Lakh [Rupees Forty Six Lakh]
or
2. Financial Criteria :
month of publication of NIT shall not be less than Rs. 57.14 Lakh [Rupees fifty seven Lakh fourteen
The average annual turnover of the bidder in the preceding three (3) financial years as on the last date of the month
preceding the
The work executed/order means the bidder should have achieved the criterion specified in the QR, even if the total
contract is not completed/closed. In case of contracts under execution as on last date of the month preceding the month
Thousand Only].
3. The bidder shall have to submit the following documents in support of meeting the QR along with their bid:
Bidder / his collaborators/associates/subsidiaries/group companies to perform the contract, should the circumstances warrant
Notwithstanding anything stated above, the Employer reserves the right to assess the capabilities and capacity of the
-2 of QR.
3.1 The bidder to submit documentary support of Clause-1 of QR.
statements from a practicing Chartered Accountant shall be considered acceptable.
(ii) In case where audited results for the last preceding financial year are not available, certification of financial
(i) While computing the annual turn over, other income shall not be considered.
3.2 Copies of audited balance sheet and profit & loss account for the preceding 03 financial years in support of Clause
8.0
such assessment in the overall interest of the Employer.
Issuance of Bidding Documents to any bidder shall not construe that bidder is considered qualified.
DY. MANAGER(C&M)PURCHASE
PHONE NO:07759-237463
E-MAIL:prakashgharat@ntpc.co.in
Websites: https://etender.ntpclakshya.co.in/sap/bc/gui/sap/its/bbpstart or www.ntpctender.com or www.ntpc.co.in
NTPC reserves the right to reject any or all bids or cancel/withdraw the NIT for the subject package without
assigning any reason whatsoever and in such case no bidder/intending bidder shall have any claim arising out of such
action.
PRAKASH M GHARAT
9.0
10.0
Address for Communication